As myself and several residents recently met with the East Kent Engineering Partnership (EKEP). Below is a summary of our meeting...
East Kent Engineering Partnership (EKEP) has been commissioned by Dover District Council (DDC) to develop plans for the coastal defences at Kingsdown. The EKEP was established in June 2007 bringing together the engineering teams of the five East Kent Coastal Authorities; Canterbury, Dover, Shepway, Swale and Thanet and are very experienced in coastal defence works.
The short-term
In the short term the EKEP will be securing the failed wall to the North of the Old Lifeboat House. This will be carried out by installing steel sheet piles at the bottom of the seawall, repairing the cracks and inserting metal tie bars which will be attached to buried concrete blocks. The worst of the nearby groynes will be patched up, by using the upper planks to fill in the holes at the base of the groynes. Shingle will then be recycled from Walmer to fill the worst depleted groyne bays.
It is felt that this will be sufficient to help the wall withstand the winter storms. The work should take place fairly quickly, the contract is out to tender now and the works will hopefully be completed by the end of October, which is excellent news.
The longer-term
The longer-term plan is to replace the 14 existing groynes with 16 realigned ones, and to replenish the beach. Over 60 thousand cubic metres of beach material is required to replenish the beach which would cost nearly £2 million if all new beach was imported.
To make the new scheme economically viable the EKEP are looking at various beach recycling options for replenishing the new groyne bays over a period of years following installation of the new groynes.
The EKEP is working on a Project Appraisal Report (PAR) which will be submitted to the Environment Agency. It is hoped that funding approval will be achieved to allow work to start next financial year. To keep costs to a minimum, piles that are in a good condition will be recycled into the new groynes.
The EKEP is cautiously optimistic that this scheme will hopefully achieve EA funding. The scheme that is being prepared by the EKEP is under the £8m estimate previously given by Halcrow, ensuring that it has a realistic chance of achieving funding.
The EKEP will keep in touch with representatives for Kingsdown, and are happy to attend a public consultation meeting once funding has been granted, to present their plans.
We were extremely encouraged by the practical, thorough approach being taken by EKEP and look forward to working with them to see these plans through to completion.
No comments:
Post a Comment